Ralph Larew, BOPARC Maintenance
Supervisor, knocking down cement block privacy wall in girls bathroom. |
Will put back original
toilet bowls with new seats. |
Handicap stall will be of
attractive wood panneling, as will all other stalls. |
Original urinals will stay
in boy's bathroom. |
Boys restroom as we found
it. Far end of room under window will become
handicap accessible facility. |
 |
 |
 |
 |
 |
|
Visit this page frequently
to follow progress. |
All fixtures and stalls
removed for new replacements, July 9-11 2006 |
Painting begins in boy's
bathroom. |
|
Old stall petitions being
removed from girl's bathroom, July 16, 2006 |
 |
 |
 |
 |
 |
| |
|
Dave Glover, BOPARC
Maintenance, installing new toilet bowl. |
Handicap toilet under
window. |
Floor Repair: brick
divider removed, boy's bathroom. |
 |
 |
 |
 |
 |
|
New handicap accessible sink
in boys bathroom. |
Floor painting begins, July
21 |
Floor painting completed in
boys bathroom. |
Custom fit stalls and vision
screens have been designed and are on order by General Glass of
Morgantown. |
Preparing floor of girls
bathroom for paint. |
 |
 |
 |
|
|
|
Handicap commode in girls
bathroom; stall panels on order. |
Floor finished; three
new commodes will be installed July 31, far end of room. |
Lounge area, girls
bathroom. |
|
|
| |
|
|
|
|